Sky Building | Development Progress
Here you will find the latest progress reports and images for the construction of the Sky Building in Newcastle Under Lyme, UK. Sky Building is a brand new development due for September 2017. This stunning, purpose built student accommodation building in Newcastle Under Lyme is the place to be for students studying in the city.
Sky Building offers a number of onsite facilities such as a cinema room, a state of the art gym, a studying lounge, a beautiful courtyard, laundry facilities and parking. Its superb location mean you are in very close proximity to Keele University (the largest campus university in the UK), Royal Stoke University Hospital and Staffordshire University.
As well as its proximity to local universities, Sky Building is also close to Newcastle Under Lyme’s local markets, culture and entertainment, making this an ideal location for students looking to engage with the buzz flowing around the town.
Sky Building is a superb investment opportunity due to a severe under-supply of student accommodation in the Keele and Newcastle-under Lyme area. Sky Building really is perfectly placed to meet the increasing demands of this market.
Sky Building | Development Progress 28/03/2017
This update about the development progress of Sky Building in Newcastle Under Lyme is dated from 28/03/2017. ‘Task Force’ meetings are being held every Thursday. These meetings provide a platform for current project discussion points and review of the Short Term Programme and planned activities.
The attached report goes into more detail about what works have been completed and how things are progressing. Important points are below.
Main Points:
- Steelwork / Decking – Metal Decking shall be complete to all floors of the main frame by close of play 28th March with remaining stud welding to these areas being carried out from tomorrow 29th March in readiness for the concrete pour preparations following straight after to enable the concrete pours on the 4th and 5th April.
- Concreting of Floors – As noted above, Industrial Concrete Floors are programmed in to return to site from 30th March to begin preparations for the concrete pours on the 4th and 5th April.
- Roofing – Richmond Roofing have progressed their works well and are 50% complete, upon completion of the remaining purloins installation by ASA they shall return to complete the metal deck roof liner and roof finishes for the second half of the roof.
Sky Building | Development Progress 26/04/2017
This update about the development progress of Sky Building in Newcastle Under Lyme is dated from 26/04/2017. Regular and daily Trade Contractor co-ordination meetings are ongoing, chaired by Core-M.
The attached report goes into more detail about what works have been completed and how things are progressing. Important points are below.
Main Points:
- Steelwork / Decking – ASA Steel Structure’s (inc Stud welders) have completed the main frame and lower podium works. Outstanding works/defects remain outstanding including roof upstands and rectification of paintwork to receive intumescent paint.
- Lift – Construction issue drawings have been issued, comments have been received from the design team to allow Schindler to finalise and re-issue. The 12 week ‘call off’ notice to commence has been issued. Electrics and plumbing will be starting next week.
- Partitioning / Drylining – Perkins Plasterers have continued to progress their works where possible. Skimming to studios has now commenced.
Sky Building | Development Progress 23/06/2017
This update about the development progress of Sky Building in Newcastle Under Lyme is dated from 23/06/2017. The Trade Contractor co-ordination meeting has indicated that key packages are at the following stages.
The attached report goes into more detail about what works have been completed and how things are progressing. Important points are below.
Main Points:
- Groundworks – Bora Construction progressing on site, namely drainage works and pouring the substation plinth and the basement slab.
- Decorations – Mist coating continued in zones 1,2 & 3. Second coating continued in zones 1 & 2. Final coats have now commenced in Zones 1 & 2.
- Kitchens – Installations to the Studio kitchens have continued including the fitted furniture and the wall panelling and headboard works.
Sky Building | Development Progress 21/08/2017
This update about the development progress of Sky Building in Newcastle Under Lyme is dated from 21/08/2017. The building received a site inspection. All floors received individual audits along with inspections to apartments that have been constructed.
The attached report indicates the important findings of the inspections and includes general observations. Important points are below.
Main Points:
- Partial sealant to boards in areas, it is recommended that a Siniat representative call to investigate and demonstrate the best way to repair and install this product. It’s also suggested that each level is checked for soundness prior to allowing bricklaying to commence.
- Roof requires water to be drained daily via pump.
- The loading of the materials seemed orderly, but with the operatives having to harness themselves onto a scaffold pole in the ceiling areas we could foresee a potential major problem with this way of loading.
Sky Building | Development Progress 04/10/2017
This update about the development progress of Sky Building in Newcastle Under Lyme is dated from 04/10/2017. Cashflow projections have now been issued. The attached report includes more information on this. Important points are below.
Main Points:
- Cashflow Projections enclosed below. These clearly outlines (i) what funds are required (ii) when the funds are required and (iii) how the funds will be spent.
- The cashflow projection graph below counts the total ‘completions’ required on a weekly basis for the next 8 weeks, in line with the construction program.
- The SKY building construction program is reliant upon the transfer of completion balances in line with the projection.
SKY Building Cashflow Projection – Aspen Woolf