One Wolstenholme Square | Development Progress
Here you will find the latest progress reports and images for the construction of One Wolstenholme Square in Liverpool, UK. These modern self-contained studio apartments are located in a very desirable city centre location near the World Heritage waterfront of Liverpool.
All studios will be finished to a modern high standard with walnut finish flooring throughout, walnut laminate doors with brushed steel hardware, dulux trade matt paint to walls, dulux trade satinwood to woodwork, TV aerial, SKY TV points, and low voltage LED lighting.
Kitchens will have contemporary high gloss white units with push to open doors & soft-close mechanisms. Contrasting grey work top, stylish stainless steel oven, hob, sink and taps and an integrated fridge/freezer
These apartments are 17% below market value with a return on investment from 86% over 5 years and 8% NET yield assured for 3 years. Free high-spec furniture packs are available for Aspen Woolf investors. All apartments are fully managed armchair investments.
One Wolstenholme Square | Development Progress 17/01/2017
This update about the development progress of One Wolstenholme Square in Liverpool is dated from 17/01/2017. We’re pleased to announce the substructures and steel frame is complete in Block A. The steel frame for Block B will be on site by the end of January 2017.
The attached report goes into more detail about what works have been completed and how things are progressing. Important points are below.
Main Points:
- Steel frame complete in Block A.
- Upper floors complete in Block A.
- Concrete foundation bases 95% complete in Block B.
One Wolstenholme Square | Development Progress 08/02/2017
This update about the development progress of One Wolstenholme Square in Liverpool is dated from 08/02/2017. In Block A the brickwork facing is in progress and the sample studios on the first floor are being fitted with kitchens, tiling is in progress and the floor finishes are all taking place. Block B is also progressing well; steel frames are in production and expected on site week commencing 6 February 2017.
The attached report goes into more detail about what works have been completed and how things are progressing. Important points are below.
Main Points:
- Pre-cast concrete stairs installed in Block A.
- External wall lining at Levels 1 to 9 in Block A.
- Concrete foundation bases 100% complete in Block B.
One Wolstenholme Square | Development Progress 13/03/2017
This update about the development progress of One Wolstenholme Square in Liverpool is dated from 13/03/2017. Site access and logistics have unfortunately caused slight delays to the construction process, so Block C foundations can’t begin until the frame for Block B is complete due of the delivery and distribution of larger materials. Similarly, construction of Blocks D and E are further complicated by access for the hotel at the rear of the site.
The attached report goes into more detail about what works have been completed and how things are progressing. Important points are below.
Main Points:
- Windows installation approximately 50% complete in Block A.
- Single ply membrane roof complete in Block A.
- Pre-cast concrete stairs installation commenced and installed in Block B.
One Wolstenholme Square | Development Progress 10/05/2017
This update about the development progress of One Wolstenholme Square in Liverpool is dated from 10/05/2017. A review of site logistics for access to each block for construction in conjunction with the interface with the adjacent hotel project has been carried out with the Contractor and anticipated completion dates can be found in the below report
The report also goes into more detail about what works have been completed and how things are progressing. Important points are below.
Main Points:
- Substructures complete in Block A.
- Concrete foundation bases 100% complete in Block B.
- Block C substructures start week commencing 8 May 2017.
One Wolstenholme Square | Development Progress 30/05/2017
This update about the development progress of One Wolstenholme Square in Liverpool is dated from 30/05/2017. The One Wolstenholme Square construction continues to progress well.
The report also goes into more detail about what works have been completed and how things are progressing. Important points are below.
Main Points:
- 2nd sample studios on first floor complete with proposed furniture in Block A
- First fix electrical commenced in Block B.
- First delivery of structural steelwork due w/c 12 June 2017 in Block C
One Wolstenholme Square | Development Progress 03/07/2017
This update about the development progress of One Wolstenholme Square in Liverpool is dated from 03/07/2017. The Employer appointed Mees Demolition to carry out the demolition of the existing buildings on the site, which is now complete.
The report also goes into more detail about what works have been completed and how things are progressing. Important points are below.
Main Points:
- Floor finishes to apartments approximately 100% and window installation approximately 99% complete in Block A.
- Facing brickwork 15% complete and concrete foundation bases 100% complete in Block B.
- Substructures completed and steelwork frame commenced on site in Block C.
One Wolstenholme Square | Development Progress 31/07/2017
This update about the development progress of One Wolstenholme Square in Liverpool is dated from 31/07/2017. We are happy to bring you another update to the One Wolstenholme Square project. Please also find new images from the build site below.
The report attached goes into more detail about what works have been completed and how things are progressing. Important points are below.
Main Points:
- Tiling and sanitaryware 100% complete in Block A.
- Insitu concrete upper floors 100% complete in Block B.
- Substructures completed and steelwork frame commenced on site in Block C.
One Wolstenholme Square | Development Progress 05/09/2017
This update about the development progress of One Wolstenholme Square in Liverpool is dated from 05/09/2017. Testing of electrical installation is currently pending whilst connection with substation is established.
The report attached goes into more detail about what works have been completed and how things are progressing. Important points are below.
Main Points:
- Snagging and inspections ongoing in Block A.
- Finishing trades progressing with tiling, kitchens and plank flooring at approximately 20% complete.
- Upper floor decking complete in Block C.
One Wolstenholme Square | Development Progress 11/10/2017
This update about the development progress of One Wolstenholme Square in Liverpool is dated from 11/10/2017. Block A’s testing of electrical installation is pending connection with the substation. The delay is due to the electric substation, thus completion is due in October 2017
The report attached goes into more detail about what works have been completed and how things are progressing in the 4 different Blocks. Important points are below.
Main Points:
- Furniture installations complete on first and second floors of Block B.
- Internal partitioning commenced to first and second floors of Block C.
- Substructures due to commence 23 October 2017 for Block D.
One Wolstenholme Square | Development Progress 10/11/2017
This update about the development progress of One Wolstenholme Square in Liverpool is dated from 10/11/2017.
The report attached goes into more detail about what works have been completed and how things are progressing. Important points are below.
Main Points:
- Snagging and inspections ongoing in Block A.
- Finishing trades progressing with tiling, kitchens and plank flooring at approximately 85% complete in Block B.
- M&E first fix now approximately 90% complete in Block C and Block D has commenced with substructures.
One Wolstenholme Square | Development Progress 04/12/2017
This update about the development progress of One Wolstenholme Square in Liverpool is dated from 04/12/2017.
The report attached goes into more detail about what works have been completed and how things are progressing. Important points are below.
Main Points:
- Snagging and inspections ongoing in Block A.
- Finishing trades progressing with tiling, kitchens and plank flooring at approximately 90% complete in Block B.
- Brickwork approximately 75% complete in Block C