Grove House | Development Progress

Here you will find the latest progress reports and images for the construction of Grove House in Manchester, UK. Leaving its commercial roots behind, the old building will be redeveloped into modern, functional residential apartments for both young professionals and families with a mix of modern 1 and 2 bedroom apartments.

Located just 1.7 miles from Manchester city centre, Grove House will provide well-planned accommodation with enough room to socialise and live, with easy access to Old Trafford football and cricket grounds and Media City and fantastic transport links to the city. All apartments come with car parking and an option of full furniture packs.

With safety in mind, these apartments have a secure entrance, on site car parking and landscaped areas. Inside, the contemporary fixtures and fittings are designed specifically for Grove House to provide a modern and resilient finish to each apartment.

This is a superb opportunity for investors with strong capital growth potential and an assured NET yield of 7% for first 2 years on a completely hassle free investment.

Grove House | Development Progress 31/05/2017

This update about the development progress of Grove House in Manchester is dated from 31/05/2017. Build works are continuing to progress well ahead of completion in July 2017.

The attached report goes into more detail about what works have been completed and how things are progressing. Important points to note are below.

Main Points: 

  • Windows fitted to all floors are now 90% complete.
  • Walls to the 3rd and 4th floors are fully boarded and are being plastered.
  • On the 7th floor the tiling to the bathrooms underway and kitchens are due to be fitted this week.

Grove House | Development Progress 09/06/2017

This update about the development progress of Grove House in Manchester is dated from 09/06/2017. With the completion date moving ever closer, progress is still on schedule despite losing a little time due to the heavy winds recently in Manchester.

The attached report goes into more detail about what works have been completed and how things are progressing. Important points to note are below.

Main Points: 

  • The fitting of windows are now at 99% completion to the full structure.
  • All walls to all levels have been plastered and a mist coat of paint applied with the exception to the communal level on the ground floor- this is due to be completed by next week.
  • Bathroom suites and ceramic tiling to walls are complete on floors 3rd, 4th, 5th, 6th 7th & 8th. Work is underway on the 1st and 2nd floors.

Grove House | Development Progress 31/07/2017

This update about the development progress of Grove House in Manchester is dated from 31/07/2017. Due to local authorities imposing extra testing to be performed on the cladding for fire safety, the construction company have communicated there will be a slight delay to the completion date, now expected end of August 2017. That said, we’re happy to also report that the Letting Agent appointed, Harper Brooks, are making great progress marketing the apartments to potential tenants. The development is extremely popular, so far it has had over 40 viewings and 10 tenant applications!

The attached report goes into more detail about what works have been completed and how things are progressing, along with a few progress images. It’s starting to really shape up! Important points to note are below.

Main Points: 

  • We are awaiting test data to be approved by a independent fire inspector before fitting all claddings to Phase 2.
  • Walls to the Ground floor, 1st floor and 2nd floor are undergoing final painting.
  • All apartments from the 3rd – 8 th floors are complete and are now undergoing snagging and a final sparkle clean.